The Windcrest Economic Development Corporation (WEDC) identified seven (7) projects consisting of certain infrastructure, repairs and improvements to roadways in the City of Windcrest that the WEDC desired to provide funding for as economic development projects.
The WEDC provided a Resolution authorizing a total of $754,125.00 for the seven (7) phase street improvement project which is in addition to funds previously allocated by the City of Windcrest for street projects.
Project number | Project to be initiated no later than | Project to be completed by | Covering certain portions of | Amount allocated |
Project 1 | January 1, 2021
| December 31, 2021
| Crestway Drive from Randolph Boulevard to Willmon Way
| $51,557.00
|
Project 2 | January 1, 2022
| December 31, 2022
| Midcrown Drive from Fenwick Drive to Walzem Road
| $345,680.00
|
Project 3 | January 1, 2021
| December 31, 2021
| Windsor Hill from Fourwinds Drive to Windsor Cross
| $61,869.00 |
Project 4 | January 1, 2022
| December 31, 2022
| Midcrown Drive from Fenwick Drive to Balfour Drive
| $69,533.00 |
Project 5 | January 1, 2022
| December 31, 2022
| Midcrown Drive from Balfour Drive to Candleglo Drive
| $94,366.00
|
Project 6 | January 1, 2022
| December 31, 2022
| Midcrown Drive from Candleglo Drive to Tidecrest Drive
| $71,520.00 |
Project 7 | January 1, 2022
| December 31, 2022
| Midcrown Drive from Tidecrest Drive to Golfcrest Drive
| $59,600.00 |